Proof Status

Current proof and open diligence are separated.

The project is not being presented as finished guest lodging today. Current photos and maps show existing site conditions only. No AI render, QGIS map, or aerial screenshot replaces ground-level silo proof.

Still Haven readiness summary showing secured facts and open diligence.
Current proof summary. It does not imply completed infrastructure, permits, or guest readiness.

What is confirmed, pending, estimated, and next

Ground-level silo documentation is being added to the investor packet before formal diligence distribution.

Project visuals must be cropped or redacted to avoid revealing exact access, road frontage, address markers, or the residence location. Current-condition images can support proof; concept renderings cannot substitute for physical proof.

Ground-level photos required before formal packet distribution

Silo 1 exterior ground-level

Confirms physical asset exists.

Silo 2 exterior ground-level

Confirms second unit potential.

Both silos in same frame

Confirms two-unit Phase 1 logic.

Silo-to-access view

Shows build and guest logistics without revealing private access details.

Silo-to-water or pasture angle

Supports experience value while staying location-safe.

Interior/current condition

Helps justify cost and scope.

Silo-to-deck/amenity sightline

Makes the guest concept tangible.

Public proof today

  • Still Haven LLC active
  • Veteran-owner verification
  • Two-silo Phase 1 scope
  • $85,000 booklet budget
  • Privacy-safe rural Hutto, Texas location framing

Open diligence

  • Land Use Agreement before capital deployment
  • Floodplain/Certificate of Compliance path
  • Licensed OSSF design and Williamson County review
  • Permit review, inspections, and authorization
  • Ground-level silo photo set